In short. Hybrid power screening starts with the problem, not the product. Before anyone sizes a battery or solar array, define what the site is trying to achieve, then gather the load profile, existing sources, continuity requirement, fuel and tariff data, and site conditions. The result is not a design but a judgement: insufficient data, worth a technical study, needs economic modelling, or needs specialist engineering. Skipping this step is how sites buy batteries that solve the wrong problem.
Start with the objective
The question “how big a battery should we buy” has no answer until the objective is clear. A battery for peak shaving, a battery for generator-off operation at night and a battery for UPS-like ride-through are three different products. Write down the primary objective and at most one secondary objective from this list: reduce fuel use, reduce generator run hours, reduce peak demand charges, increase resilience against outages, use more solar, support remote or off-grid operation, or prepare for a microgrid. If the owner wants all of them equally, the screening must first force a ranking.
The data to gather
| Area | Data | Why it matters |
|---|---|---|
| Load | Peak, minimum and normal kW; daily kWh; hourly profile; seasonal change; largest motor or load step | Sets battery kW, kWh and generator duty |
| Existing system | Utility supply, generators, UPS, transformers, switchgear, any PV or BESS | Defines what can be reused and where new equipment connects |
| Continuity | Which loads are critical and how long they must run | Sets reserve energy and architecture |
| Generators | Number, rating, hours, typical loading, verified fuel consumption, maintenance history | Baseline for any fuel or hours saving |
| Solar resource | Location, available area, orientation, shading, existing yield data | Sets realistic PV production |
| Grid | Reliability, outage frequency and duration, paralleling and export permission | Decides grid-connected or islanded design |
| Fuel | Type, cost, supply reliability, storage | Endurance and operating cost |
| Commercial | Tariff, demand charges, annual hours, project horizon | Payback and financing |
| Environment | Ambient, dust, coastal exposure, space, access | Derating, cooling and enclosure |
Not every item is needed for every project, but the load profile almost always is. A site without interval data should install a logger for two to four weeks before screening goes further; the generator loading calculator helps make sense of what it records.
Turning data into a technology pathway
Once the objective and data are in hand, the pathway usually narrows to one or two of these: generator plus battery, as in generator and BESS systems; solar plus generator; solar plus generator plus battery; a grid-connected microgrid; or an off-grid microgrid. Some sites turn out to need none of them, and a better-maintained generator, a load management scheme or a correctly sized replacement set is the honest recommendation.
A screening example (illustrative)
A cold store near Hyderabad asks for a battery to cut diesel use. Its data show a 250 kVA set running about 1500 hours a year at around 40% load, with most hours in two-hour summer outages. The low-load problem is modest and annual diesel is limited, so a fuel-saving battery would pay back slowly. The more useful finding is that motor restarts after each outage trip the generator twice a month. The pathway becomes staged restart control and a review of generator sizing first, with a battery reconsidered later.
Engineering flags
Screening also lists what is still unknown. Typical flags are: load profile data required; battery energy duration not defined; motor transient review required; grid interconnection review required; fuel cost data required; renewable yield study required; microgrid control study required; and specialist battery safety review required. Flags are not failures; they are the scope of the next stage.
Classifying the opportunity
Projects that pass then move to the hybrid capacity screening tool and detailed study. The output of screening is one of four verdicts. Insufficient data means the objective or load profile is not yet known. Technically worth screening means the concept fits and a study is justified. Economic modelling required means the technical concept is clear but tariffs, fuel prices or hours are uncertain. Specialist engineering required means the project involves critical loads, grid paralleling or complex integration. A screening should never end with a precise battery rating or a guaranteed fuel saving percentage, because neither can be stated without the modelling that follows.
Simple payback (years) = Net capital cost ÷ Annual net saving
Net saving is fuel, demand charge and maintenance avoided minus added maintenance and battery degradation. A system whose net annual saving is one fifth of its installed cost has a five-year simple payback (illustrative); the figure is only meaningful once each saving is backed by site data.
A quick screening in numbers (illustrative)
Screening turns a few figures into a first view of whether a hybrid is worth a detailed study. A site has a 320 kVA set, or 256 kW at 0.8 power factor, running 3000 hours a year. Its average load is 70 kW, about 27% of rating, and its fuel records show about 0.34 litres per kWh, so it uses about 70 × 3000 × 0.34, or 71,400 litres a year. The daytime load averages 100 kW for 10 hours and the night load 40 kW, and the roof can take about 120 kW of solar panels.
| Indicator | Value | What it suggests |
|---|---|---|
| Average generator load | About 27% | Light-load running; a battery or smaller set could help |
| Fuel per kWh | 0.34 litres | Well above the 0.26 to 0.28 at healthy load |
| Running hours | 3000 a year | Enough hours for savings to matter |
| Daytime load against solar | 100 kW against about 120 kW of panels | Solar can cover much of the daytime energy |
| Night load | 40 kW | Battery could carry part of the night |
The screening shows a promising case: many hours, light load and good solar potential. If the set ran at the healthier 0.27 litres per kWh for the same energy, it would use about 56,700 litres, so improved loading alone points to about 14,700 litres a year before any solar contribution. A detailed hour-by-hour study then tests that estimate against the real load profile.
Red flags that end a screening early
- Very few running hours, so savings cannot repay the equipment.
- No space, structure or approval route for solar or a battery.
- A generator controller that cannot accept external start and stop commands, with no plan to replace it.
- Loads with large, frequent steps that the battery inverter cannot support without a much larger rating.
- No one available to operate and maintain the added equipment.
What a screening should deliver
A screening ends with a short report: the data used and its source, the key indicators, a first sizing of solar, battery and generator, the estimated range of fuel and running-hour savings, the risks and red flags found, and a clear recommendation to proceed to detailed design, to change the scope, or to stop. Stating a range rather than a single number for savings is honest, because the detailed study often moves the figure.
Moving to detailed design
- Log the load for at least two weeks, including a weekend, at intervals of a few minutes.
- Collect the generator maker fuel curve and load acceptance data.
- Obtain solar resource data for the site and confirm the roof or ground area.
- Simulate hour by hour over a typical week and the worst outage week.
- Choose control rules and battery size, and repeat the simulation for alternatives.
- Confirm approvals, safety design and maintenance arrangements before ordering.
Who should be involved
A good screening brings together the person who pays the fuel bills, the person who runs the generator, and the person responsible for the electrical installation. Each holds data the others lack: fuel invoices, running logs, load records, outage history and the condition of the existing set. A short meeting with these three at the start often saves weeks of later questions, and their agreement on the screening outcome makes the next step straightforward to approve.
The same group reviews the detailed study before any order is placed, so that the assumptions about load, outages, fuel and maintenance are confirmed by the people who know the site best, and the final decision rests on figures everyone accepts.
A short written note of who attended and what was agreed keeps the project on track.
Common mistakes
- Requesting a battery quotation before defining the objective. The supplier sizes for whatever is cheapest to offer.
- Screening from monthly bills without interval data. Peak durations and low-load hours are invisible and the sizing is guesswork.
- Using the generator’s rated fuel consumption instead of measured litres. The baseline is wrong and so is every saving.
- Ignoring the motor restart problem because the brief said fuel saving. The real reliability issue stays unsolved.
What to send us
Send the stated objective, at least two weeks of interval load data or a logger export, generator nameplates with run hours and fuel records, the single-line diagram, recent electricity bills and photographs of the generator room and main switchboard. Mention any planned expansion. Submit through the application engineering enquiry and we will return a screening verdict with the flags to resolve.
Questions engineers ask
What figures do I need for a first hybrid screening?
Generator rating, running hours a year, fuel used, average load, the daytime and night loads, and the space available for solar and a battery. From these, a screening estimates the load share, fuel per kWh and likely savings range, and shows whether a detailed study is worthwhile.
What does a high fuel per kWh figure tell me?
That the set is running inefficiently, usually at light load. In the illustrative site, 0.34 litres per kWh against about 0.27 at healthy load means improved loading alone could save about 14,700 litres a year on 210,000 kWh, before any solar contribution is counted at all.
What ends a hybrid screening early?
Very few running hours, no space or approval route for solar or a battery, a generator controller that cannot accept external commands with no plan to replace it, very large frequent load steps, or nobody to operate and maintain the added equipment. Any of these usually stops the project.
What does a good screening report contain?
The data used and its source, the key indicators, a first sizing of solar, battery and generator, a range of fuel and running-hour savings, the risks and red flags found, and a clear recommendation to proceed, change scope or stop. A range is more honest than a single number.
How long does a hybrid screening take?
With good interval data and generator records, a first screening can be done in days. Most of the elapsed time is usually spent collecting the data, which is why a logger installed early saves weeks. A few weeks of one-minute logging covers most screening needs.
Do I need a site visit for screening?
Not always for the first pass, if photographs, the single-line diagram and data are good. A visit becomes necessary before detailed design to verify space, switchgear condition, earthing and cable routes. The visit also checks the generator condition and controls, and confirms that the loads and their behaviour match what the data shows.
Can screening tell me how much fuel I will save?
It can give a range and say whether the saving is likely to be material. A firm figure needs hourly modelling of load, solar and generator behaviour against a measured baseline. The measured baseline comes from fuel records and generator hours over the same months, so the result after the project can be compared fairly.
What if the screening says a hybrid is not worth it?
That is a useful result. It usually points to a cheaper fix such as load management, generator resizing, better maintenance or staged restart, and it avoids spending capital on equipment that would not earn its cost. The screening report records why, with the data behind it, so the decision can be revisited if tariffs or loads change.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.