In short. Synchronising controls bring an incoming generator’s voltage, frequency and phase angle into agreement with a live bus, then permit the breaker to close only while those conditions hold, allowing for the breaker’s closing time. The scheme has three parts: an active synchroniser that nudges governor and AVR, an independent synchronism check that blocks closure outside the window, and reliable dead-bus detection. Out-of-phase closure can bend a crankshaft, so the negative test matters as much as the positive.
What has to match before the breaker closes
Two alternating sources can be connected only when they are electrically indistinguishable at the instant of closure. Four quantities are compared, and the acceptance window for each is set at commissioning from the alternator and breaker data.
| Quantity | Typical acceptance window | Consequence of a mismatch at closure |
|---|---|---|
| Phase sequence | Must be identical, checked once at installation | Direct short circuit between phases, severe damage |
| Voltage magnitude | Within 3 to 5% of bus voltage | Reactive current surge, AVR disturbance |
| Frequency (slip) | Within 0.1 to 0.2 Hz of bus frequency | Power swing, governor hunting, possible reverse-power trip |
| Phase angle | Within 5 to 10 electrical degrees at the moment contacts touch | Torque transient on the shaft, high current, tripped breaker or mechanical damage |
The phase-angle window is the one that does the damage when it is wrong. Closing a 500 kVA set 30 degrees out produces a current comparable to a short circuit and a torque pulse the coupling and crankshaft were not designed for. The underlying theory is set out in generator synchronisation.
The three functions in a synchronising scheme
The active synchroniser
The synchroniser measures the incoming and bus voltages and sends raise and lower pulses, or an analogue bias, to the governor and the AVR until the incoming set drifts slowly into the window. A small positive slip of around 0.05 to 0.1 Hz is usually targeted so that the incoming set takes a little load on closure rather than motoring, after which control hands over to the load-sharing controls. On a mechanical governor the response is slower and less linear, which affects how long synchronising takes.
The synchronism-check permissive
A sync-check function, ANSI device 25, is a separate judgement that the conditions are within limits right now. It does not adjust anything. It simply permits or blocks the close command. In the simplest schemes it lives in the same controller as the synchroniser. For higher-consequence plants, such as utility paralleling or large multi-set data-centre buses, an independent sync-check relay in series with the close circuit guards against a failure or mis-setting of the primary controller.
Breaker closing time compensation
An air circuit breaker takes 40 to 100 milliseconds between the close command and contact touch. At a slip of 0.1 Hz the phase angle moves 36 degrees per second, so a 100 millisecond breaker moves 3.6 degrees during closing. The controller is set with the breaker’s measured closing time so that the command is issued early and the contacts touch at the target angle.
Dead bus versus live bus
The first set to connect to an unenergised bus does not synchronise. It simply closes onto the dead bus and establishes voltage and frequency for the others to match. That is a different control path with different permissives, and the controller must choose correctly between them every time. The dangerous failure is a bus that is actually live but which the controller believes is dead because its bus voltage transformer fuse has blown, its sensing wire is broken, or a breaker position contact is reporting open when the breaker is closed. The controller then closes the incoming set without synchronising onto an energised bus.
Defences are straightforward and should all be present. Monitor the bus VT fuses or use a VT-fail detection function. Use breaker position feedback from both a normally-open and a normally-closed auxiliary so that a disagreement is detected. Require two independent indications of dead bus, typically bus voltage below about 20% and no other generator or utility breaker closed, before permitting a dead-bus close. The logic is developed further under dead-bus, live-bus and sync-check control logic.
Generator-to-generator and generator-to-utility are different problems
Paralleling two of your own sets takes place inside your own installation under your own protection settings. Synchronising a set to the DISCOM supply, even for a few seconds during a closed-transition transfer, connects the set to the public network. That brings the utility’s interconnection conditions, its protection requirements for loss-of-mains detection, and in many cases a written approval before the scheme is energised. The protection behind it must satisfy the utility, including reverse-power, frequency and loss-of-mains functions. The closed-transition case is covered in closed-transition ATS and the wider topic in generator paralleling.
Sensing and wiring are where schemes fail
Synchronising controllers almost never make an arithmetic error. The problems are at the terminals. Voltage sensing taken from the wrong side of a breaker, a VT with the secondary polarity reversed, a phase swapped in the bus sensing all produce a controller that reports a phase difference that is not there, or worse, reports none when there is one.
Commissioning therefore begins with a phasing check: with the incoming set running and its breaker open, a voltmeter across the open breaker on each phase should read twice phase voltage when the sets are 180 degrees apart and near zero when in phase, and the controller display should agree. Only after the sensing is proven does any automatic synchronising take place.
Commissioning and the negative test
A synchronising scheme is accepted on evidence of both behaviours, that it closes when it should and that it refuses when it should not. The positive test synchronises each set to the bus several times and records the voltage difference, slip and angle at the moment of closure from the event log. The negative test deliberately sets the incoming voltage several percent out, then the frequency out, and confirms the close is blocked and alarmed each time. Settings and breaker closing times are recorded against each breaker, and the handover notes state which transitions were tested. The switchgear side of the work is described in synchronising and switchgear service.
The window, in numbers, and why the breaker closes early
The conditions described above are usually given as a list of things that must match. On a real synchroniser each is a setting with a number in it, and the numbers are not arbitrary: each one is the point where closing stops being harmless and starts costing something.
| What is checked | Usual window | Why that figure | What a wider setting costs |
|---|---|---|---|
| Voltage difference | Within about 5% | The difference drives reactive current the instant the contacts meet, and it has nowhere to go but the two machines | A reactive surge and a kick on the regulators, repeated every time the set is paralleled |
| Frequency difference, the slip | 0.1 to 0.3 Hz, with the incoming set slightly fast | Slow slip gives the breaker time to close inside the phase window; slightly fast means the set takes load rather than motoring | Below 0.05 Hz the machines can drift together for minutes and never close; above 0.5 Hz the angle moves faster than the breaker can keep up with |
| Phase angle | Within about 10 degrees at the moment of contact | Torque on the shaft and current in the windings both rise sharply with the angle | A mechanical shock through the coupling that no alarm records and no inspection sees |
| Phase rotation | Identical, proved once | Not a setting but a wiring fact, and the only item on this list that is catastrophic rather than merely harmful | Nothing, if it is proved at commissioning and after every cable alteration |
The advance angle, and the arithmetic behind it
The second row is the one that explains the whole scheme. A breaker takes time to close — typically 60 to 100 milliseconds from the command to the contacts touching — and the phase angle keeps moving during that time. So a synchroniser does not issue the close command at zero degrees; it issues it early, by exactly the angle the phase will travel while the breaker is operating:
advance angle = slip in hertz × breaker closing time in seconds × 360
At 0.2 hertz of slip and an 80 millisecond breaker, that is 5.8 degrees of advance. At 0.5 hertz and 100 milliseconds it is 18 degrees, which is already outside the window the scheme is trying to hold. The arithmetic is the reason slip is kept low: it is not that a fast slip is dangerous in itself, but that it makes the breaker’s own delay too large a share of the window.
Two consequences follow, and both are commissioning items rather than design ones. The breaker closing time in the synchroniser’s settings has to be the real closing time of the breaker that is fitted, measured, not the figure from a similar breaker or a default left in the controller — an 80 millisecond setting on a 140 millisecond breaker closes the set 4 degrees late every time. And when a breaker is replaced or overhauled, that setting is part of the work: a reconditioned mechanism that closes more slowly than it used to will quietly move every subsequent closure further out of phase, with nothing on any display to say so.
One practical note on patience. At 0.1 hertz of slip the two systems come back into phase once every 10 seconds, so a synchroniser that appears to be doing nothing may simply be waiting for its next opportunity. The instinct to widen the window to make it close faster is the wrong one: the right response is to check that the governor is actually holding the small frequency offset the scheme needs, because a synchroniser that never gets a chance is usually looking at a speed loop that is hunting rather than at a window that is too narrow.
Common mistakes
- Treating a missing bus voltage reading as a dead bus. The set closes unsynchronised onto a live bus and the result is a bent coupling or a destroyed breaker.
- Using the catalogue breaker closing time rather than the measured one. Contacts touch several degrees off target and every closure is harder than it should be.
- Copying synchronising settings from another plant. Different alternators, breakers and governors need different windows, and a window that is right for one set can be unsafe for another.
- Accepting commissioning because all the breakers ended up closed. Without the event log and the negative test there is no evidence the scheme would refuse an unsafe closure.
What to send us
Send the single-line diagram of the generator bus with breaker types and ratings, the nameplates of each set and its controller, and a note on whether utility paralleling is intended. If a scheme is misbehaving, export the controller event logs around the failed or rough closures and send them with photographs of the sensing wiring. Use the application engineering enquiry for new or modernised synchronising schemes.
Questions engineers ask
Why does the synchroniser close the breaker before the phase angle reaches zero?
Because the breaker takes time to close and the angle keeps moving while it does. The command is issued early by exactly the angle the phase will travel during that closing time: slip in hertz times the closing time in seconds times 360. At 0.2 hertz of slip and an 80 millisecond breaker that is 5.8 degrees of advance. The closing time in the settings must be the measured time of the breaker actually fitted.
What slip should a synchroniser be set to?
Usually 0.1 to 0.3 hertz, with the incoming set slightly fast so it takes load rather than motoring when the contacts meet. Below about 0.05 hertz the two systems can drift alongside each other for minutes without ever closing. Above 0.5 hertz the angle moves faster than the breaker can keep up with: at 0.5 hertz and a 100 millisecond breaker the advance needed is 18 degrees, already outside the window the scheme is trying to hold.
What happens if a generator closes out of phase?
The two sources try to pull each other into step instantly. The current can approach short-circuit levels and the torque pulse on the shaft can exceed the design value several times over. Typical outcomes range from a tripped breaker and an AVR fault through to a sheared coupling, a cracked flywheel housing or a damaged alternator winding. It is the one control failure that destroys hardware in a single event.
Can two generators of different makes be synchronised?
Yes, provided both can accept speed and voltage bias from the synchroniser and both have compatible alternator characteristics for subsequent load sharing. The controller does not care about the engine brand. What matters is that the governor and AVR interfaces are engineered, the sensing is correct, and load sharing after closure has been designed.
Is manual synchronising still acceptable?
It can be, under a written procedure, with a synchroscope or check-synchroniser display and an independent sync-check relay that blocks the manual close button outside the window. It should never rely on an operator’s eye alone. Most plants keep manual synchronising as a fallback and use automatic synchronising for normal operation.
How long should synchronising take?
Typically 5 to 30 seconds once the incoming set is up to speed and voltage, depending on governor response and the initial frequency difference. Much longer than that usually points to a slow mechanical governor, an unstable AVR, or a slip target set too close to zero so the angle takes a long time to come round.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.