In short. Reddy Generators works through the same sequence on every job: understand why power is needed, assess the load and site, engineer the rating and supporting systems, verify the data, then supply, install, commission and maintain. The scope varies from a single rental set to a synchronised plant, but each stage removes a specific uncertainty before money or equipment is committed, and the customer sees what was assumed at every step.
Why a fixed sequence matters
Generator problems found during commissioning are expensive; problems found during a real outage are worse. Almost all of them can be traced to a step that was skipped: the load was never measured, the motor starting was never checked, the transfer logic was never tested on load. A consistent sequence makes skipped steps visible. It also lets a customer see where their job stands and what information is still missing.
Stage one: understand and assess
Understand the purpose
We start with three questions. What needs power? Why must it continue? What happens if it stops for a second, a minute or an hour? A cold store, a dialysis unit and a builder’s tower crane all need generators, for very different reasons, and those reasons drive everything that follows.
Assess the load and site
We then gather facts: connected and running loads, the largest motors and how they start, UPS and variable-speed drive loads, voltage, phase and frequency, expected hours of operation, and site conditions such as ambient temperature, altitude, space, ventilation and access. For larger jobs this becomes a formal Load Study and Generator Site Survey.
Stage two: engineer and select
With the facts in hand, the engineering work covers steady-state demand, transient performance during motor starting and load steps, power factor, the order in which loads are connected, derating for heat or altitude, redundancy, controls and fuel autonomy.
Required kVA = (Prun / PF) × (1 + m) / d
Here Prun is the simultaneous running load in kW, PF is the load power factor, m is the design margin for growth and unknowns, and d is the derating factor for ambient temperature or altitude from the manufacturer’s data.
(illustrative) A site with 160 kW running load at 0.8 PF, a 20% margin and a derating factor of 0.95 for a hot plant room gives (160 / 0.8) × 1.2 / 0.95, which is about 253 kVA. A 250 kVA set would be marginal on paper, so the next standard size up would be checked, and the largest motor start would then be verified against that set’s transient data before the choice is fixed.
The output of this stage is an architecture: a single set, several sets in parallel, standby or prime duty, rental or purchase. Then the supporting systems are defined: controller, AMF or ATS panel, synchronising equipment where needed, breakers and protection, cables, fuel storage, ventilation, exhaust and earthing.
Stage three: verify, deliver and commission
Before anything is ordered or dispatched we verify the model data against the current manufacturer information, confirm CPCB IV+ compliance for new sets in the applicable range, check that the site interfaces work, and list the assumptions that remain. Permanent sales and rental deployments then follow different logistics, but both end on site.
Where installation is in scope, the set is positioned, connected, inspected, configured, tested and documented. Testing proves what it is meant to prove: a no-load run proves the set starts; a load test proves it carries the load; a mains-fail simulation proves the AMF or ATS transfers and retransfers correctly. Our checklist is in Generator Commissioning Checklist.
| Stage | Key output | Uncertainty removed |
|---|---|---|
| Understand | Purpose and outage consequence | Why the set is needed |
| Assess | Load list, site data | What it must carry and where |
| Engineer and select | Rating, architecture, supporting systems | Whether it will perform |
| Verify | Confirmed data and assumption list | Whether the data is current and true |
| Deliver and commission | Installed, tested system and records | Whether it works on this site |
| Operate and maintain | Service plan, test records | Whether it will keep working |
Stage four: operate, maintain and improve
Reliability depends on what happens after handover. Standby sets in particular fail from neglect: flat batteries, water in the fuel, stuck injectors, perished hoses. A maintenance plan under an AMC keeps those risks in check. When performance does deteriorate, we follow a diagnostic chain of symptom, measurement, diagnosis, intervention and verification, so that the repair addresses the cause and not only the alarm. See Preventive Maintenance and Capability & Support Model for the services involved.
What each stage produces
| Stage | Output the customer receives | Uncertainty it removes |
|---|---|---|
| Understand and assess | A short statement of what must stay powered, for how long, and the consequence of losing it; a load list or measured data | Whether the problem has been defined at all |
| Engineer and select | The rating and its basis, the starting method for the largest motor, the changeover and installation scope | Whether the set will carry the hardest moment, not just the average |
| Verify, deliver and commission | Installed set, load test record, changeover proved, staff briefed, handover file | Whether what was designed actually works on site |
| Operate, maintain and improve | Service reports, test records, recommendations as the load changes | Whether the set will still work on the day it is needed years later |
How the stages scale with the job (illustrative)
| Job | Understand and assess | Engineer and select | Verify and commission |
|---|---|---|---|
| 15 kVA set for a clinic | One call and photographs of the panel | Load added up, the largest motor checked | Changeover tested, staff shown the controls |
| 250 kVA set for an office building | Site visit, load list, lift and pump details | Rating, starting methods, AMF panel, cable route | Load bank test, simulated mains failure, handover file |
| Three paralleled sets for a factory | Measured load logging, outage history, expansion plans | Studies for fault level, protection and load shedding | Each set tested, then synchronising, sharing and set-trip tests |
The logic is identical at every size; only the depth of each step changes.
The maintenance standard we work to
Once a set is in service, the routine is fixed and recorded. Engine oil and filters are changed every 250 to 500 running hours or six months, whichever comes first, and coolant is replaced every year. Between those, regular runs on load, battery and charger checks, and a yearly load bank test keep a standby set ready. Each visit leaves a report with the readings taken and the next date due, so the condition of the set is never a matter of memory.
Taking over a set or a project from someone else
Many jobs start part-way through someone else’s work: a set installed by another supplier, a project left unfinished, or a set bought second-hand with no history. The first step is always to verify: read the nameplates, check the installation against the load and site, test the set on load, and record what is found. Only then is a recommendation made, so that nobody inherits an assumption without knowing it.
When the plan changes mid-job
Jobs change: a load is added, a room moves, a delivery slips, a site discovers an old cable that cannot be reused. Each change goes back through the relevant stage rather than being absorbed silently. A new load returns to engineering and select, to check the rating and the largest start; a new room returns to verify, to check air, exhaust and access; a new date is confirmed with everything that depends on it. The customer sees the change, its effect and its cost in writing before work continues.
The records that come with every job
- The requirement as agreed, with any figures marked as measured or estimated.
- The proposal and any changes made during the job.
- The commissioning and load test records with readings at each step.
- Protection and changeover settings as left on site.
- Service reports for the life of the set.
Kept together, these make every later decision faster and safer, whoever makes it.
A job walked through the four stages (illustrative)
A hospital wing asks for a larger generator because its existing 160 kVA set tripped during an outage. Understanding the need shows the trip happened when a 30 kW chiller restarted with the other loads already running. Assessing the load shows a running demand of about 95 kW, well within the existing set.
Engineering the answer shows the problem is the restart sequence, not the size: a time delay on the chiller restart and a soft starter on its motor bring the start within the set’s capability. Verification is a simulated mains failure with the full load connected, recording voltage and frequency through every restart. The customer keeps the existing set, gains a tested restart sequence, and avoids buying a larger set that would have run lightly loaded for years.
Not every job ends with a smaller answer, but every job ends with the reason written down.
Common mistakes
- Jumping from connected load straight to a kVA figure, which usually oversizes the set and wastes capital and fuel.
- Selecting the set before checking the largest motor start, which can leave a set that trips or stalls every time that motor starts.
- Treating commissioning as a no-load run, which proves nothing about the set’s ability to carry the facility or transfer correctly.
- Ending the relationship at handover, which leaves a standby set untested until the day it is needed.
What to send us
To start the sequence, send the site location, a load list or DB panel readings, the loads that must stay on, any large motors with their starting method, and photos of the proposed generator location and existing panels. If you already have a set, include its nameplate photo and hours. Submit through the application engineering enquiry and we will tell you which information is still missing.
Questions engineers ask
How often should generator oil be changed?
Engine oil and filters are changed every 250 to 500 running hours or six months, whichever comes first, and coolant is replaced every year. A standby set that runs few hours still needs the six-month change, because oil ages and collects moisture in the engine even when it is not running. Each change is recorded in the service report with the hours.
What records do I get at the end of a job?
The requirement as agreed with figures marked as measured or estimated, the proposal and any changes made during the job, the commissioning and load test records with readings at each step, the protection and changeover settings as left on site, and from then on a service report after every visit. Together they form the generator file for the site.
Do small jobs go through the same stages?
Yes, in proportion. For a 15 kVA set in a clinic the stages may take a single conversation and a site photo. For a multi-set plant they become formal studies and documents, but the logic is the same: define the need, check the hardest moment, verify on load and record what was found, so nothing is left to memory.
What margin do you normally add when sizing a standby generator?
A margin of around 15 to 25% over the verified running load is common for standby duty, adjusted for known future load and site derating. The margin is never a substitute for checking motor starting and UPS behaviour, and too large a margin brings light loading, wet stacking and poor fuel economy of its own.
Is a load-bank test part of commissioning?
Where the real load cannot be applied safely or fully on commissioning day, a load-bank test is the reliable way to prove the set at rated output. Whether it is included is agreed in the scope. The test steps the load up to the rating, holds each step until temperatures settle and records the readings for later comparison.
Can you take over a project another supplier started?
Yes. We would begin with the verify stage, checking the installed equipment and existing documents against the load and site, before continuing with commissioning or maintenance. Nameplates are read, the set is tested on load and the findings are written down, so that nobody inherits an assumption without knowing it is there.
Technical content reviewed by D. Srinivas Reddy, Managing Partner and Service Engineer, Reddy Generators. Last updated 19 October 2026.