Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Load-Shedding Requirement and Priority Planning Guide

How to decide whether load shedding is needed and plan it: capacity shortfall cases, shed tiers, triggers, staged shedding and restoration, with a worked shortfall example.

In short. Load shedding is needed when available generation can be less than the load, for example after a unit trips or when only a standby set is available. Find the shortfall in each case, decide which loads can go, in which order, and what triggers each stage.

Step 1: Find the cases

CaseAvailable capacityLoad to carry
Normal, all unitsFullFull
One unit failed or in maintenanceTotal minus the largest unitCritical plus essential
Single generator on standbyOne unitPriority loads only
Temporary or rental sourceRental capacityLimited set
Fuel or derating limitReduced capacityReduced

Step 2: Compute the shortfall

Shortfall (kW) = Load demand − Available capacity (after derating and loading limit)

Example (illustrative): load 2,200 kW, three 1,000 kW units. With one tripped, available is 2,000 kW at 100 per cent, but with a target loading of 90 per cent it is 1,800 kW. Shortfall is 400 kW, so at least 400 kW of load must be shed, with margin.

Step 3: Choose what to shed

Use the classification. Shed the lowest tier first, and check the total. See critical-load classification.

Step 4: Plan the stages

The scheme should shed enough in the first action for each case, with later stages for frequency or overload triggers. See load shedding and priority control.

Step 5: Triggers and speed

Step 6: Restoration

Plan staged restoration once capacity returns. See restoration sequencing.

Checks

Worked illustration

In the case above, the 400 kW shortfall is met by shedding 300 kW of comfort cooling (Tier 4) and 200 kW of a deferrable process line (Tier 3), total 500 kW, giving margin. The plan lists those feeders, the triggers and the order, and is tested by simulating a unit trip.

Do you need load shedding?

SituationNeed
One generator carrying nearly all loadSimple overload shedding of non-essential loads
N+1 generators, load fits NShedding for double failure or abnormal events
Loads exceed generator capacity by designMandatory, as a normal operating feature
Island or hybrid operationMandatory, with battery state-of-charge triggers

Shedding amount (illustrative)

Sets online 3 × 500 kW. One trips. Available = 2 × 500 × 0.9 (safe loading) = 900 kW. Load before the event 1,300 kW. Shed at least 400 kW. Choose shedding blocks: comfort HVAC 250 kW, process auxiliary 200 kW, giving 450 kW. The shed is done in under a second by a fast controller, ahead of frequency decay.

Design requirements

  1. A priority list approved by the operator.
  2. Triggers: source loss, overload, frequency.
  3. Shedding speed suited to the generator’s response.
  4. Restoration rules to avoid re-tripping.
  5. Test with real breakers.

What to avoid

See load shedding automation and load shedding engineering.

Common mistakes

What to send us

Send the load list, classification and generator arrangement. Send your application details. See also load-shedding automation.

Questions engineers ask

When is load shedding not needed?

When any credible failure still leaves enough capacity for the entire load. That usually needs larger N+1 capacity.

How much load should I shed?

At least the shortfall, with margin, for each case.

Is manual shedding acceptable?

For slow events perhaps, but generator trips need fast automatic action.

How do I test the scheme?

Simulate each case, including a unit trip, and record the response.

Figures are illustrative. Shed lists must be validated with operations.

CallWhatsAppEnquire
STAGING PREVIEW · NOT INDEXED