Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Load-Shedding Automation and Priority Logic

How automatic load shedding works: priority tiers, fast event-based and slow shedding, under-frequency backup, shed tables, restoration and tests that prove the plant survives a source loss.

In short. Load shedding removes lower-priority loads so the remaining sources stay stable. It must act faster than the plant collapses, shed the right amount in the right order and never shed life-safety loads. Tests with real source trips prove it works.

Types

TypeTriggerSpeed
Fast event-basedLoss of a source or breaker, known in advanceTens of milliseconds
Slow overload-basedMeasured overload or limit exceededSeconds
Under-frequencyFrequency falls below thresholds in stagesFractions of a second to seconds; backup to the others
Under-voltageVoltage falls in a weak systemContext dependent

Priority tiers

  1. Life safety and emergency systems: never shed.
  2. Critical process and IT.
  3. Essential mechanical systems.
  4. Production loads that can pause.
  5. Comfort and non-essential loads: shed first.

See load prioritisation.

Shed table

For each credible event, such as the loss of generator 1 or utility, the shed table lists which loads to trip, by how much power and in what order. Its size must match the capacity left and the real-time load, which is why it relies on metering of the shed feeders.

Design checks

See also load shedding.

Illustrative example

A plant runs three 1,000 kW generators with 2,200 kW load. If one trips, the remaining two (2,000 kW) are overloaded by 200 kW. The shed table trips 300 kW of chillers and process pumps within 100 ms, frequency stays above its limit, and the standby set takes over in 20 seconds.

Why shedding must be automatic

When a generator is overloaded, frequency falls within seconds, protections trip and the whole bus can black out. Operators cannot respond in that time. Automatic load shedding removes selected loads quickly so the remaining supply survives.

TriggerSpeedUse
Static (capacity-based)Fast, on loss of a sourceShed before frequency falls, based on available kW
Dynamic (frequency-based)Hundreds of msBackup when something unexpected happens
Rate of change of frequencyFastest on large disturbancesLarge step loads or source trips

Priority table (illustrative)

PriorityLoad classShed order
1Comfort HVAC, water heatingFirst
2General process, auxiliary pumpsSecond
3Important processThird
4Critical and life safetyNever

Capacity-based logic

Shed required = connected load − available generation × safe loading factor

If three 500 kW sets are online with 1,400 kW load, and one trips, available is 1,000 kW × 0.9 = 900 kW, so at least 500 kW must be shed immediately.

Design points

See load shedding and load restoration.

The master engineering question

For each credible loss of source, will the load that is shed arrive before frequency falls to the point of collapse, and is it the load the site would choose?

What to send us

Send feeder list, priorities and generator data. Send your application details.

Questions engineers ask

Is under-frequency shedding enough?

Often not, because it reacts after frequency has already fallen. Use it as a backup.

How much load to shed?

Enough to restore balance, plus margin, calculated for each event.

Who sets priorities?

Operations and safety owners, reviewed by engineering.

How is it tested?

By simulated or controlled trips with monitoring.

Values are illustrative. Shed tables must be project-specific.

CallWhatsAppEnquire
STAGING PREVIEW · NOT INDEXED