Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Critical-Load Shedding and Priority Control

How load shedding protects generators and critical loads: priority lists, trigger types, timing, restoration and the settings that avoid blackouts and nuisance shedding.

In short. Load shedding disconnects less important loads so the available sources can carry the important ones. It is needed when generator capacity is limited, when a unit fails, or when frequency or voltage begins to sag. A good scheme has a clear priority list, fast and correct triggers, and a planned way to bring loads back.

Why shed load

Priority list

PriorityLoad typeAction
1Life-safety and mission-criticalNever shed
2Essential process and servicesShed last
3Important but deferrableShed after lower tiers
4Comfort and non-essentialShed first

Build the list from the classification in critical, essential and mission-critical power.

Trigger types

Timing

Shedding for a generator trip must be fast, within tens to hundreds of milliseconds in many cases, or the remaining generators may stall. Dedicated relays or PLCs with direct wiring are often used for the fast path. See load-shedding automation.

Settings to avoid nuisance shedding

Restoration

Bring loads back one tier at a time after the generators are stable and capacity is confirmed. Do not restore everything at once: the combined step may cause a second collapse. See restoration and restart sequencing.

Worked illustration

A plant has three 1,000 kW generators and 2,200 kW of load. Capacity with three units is 3,000 kW, enough. If one generator trips, 2,000 kW remains against 2,200 kW load, so 200 kW or more must go. The static scheme knows which tier to shed at once, say 300 kW of comfort and deferrable load, and the generators stay stable. Without it, the two units overload, frequency drops and the plant may trip into a full blackout.

Testing

When capacity falls short

Events such as a failed generator, a degraded UPS or a cooling loss leave less capacity than load. Without a plan, the whole bus fails. Load shedding drops the least important loads first to protect the most important.

TierExamplesAction
1 (protect always)Life safety, control, IT core, monitoringNever shed
2Production-critical, key coolingShed only in severe shortage
3Important but deferrableShed in shortage
4Comfort and convenienceShed first

Triggers

  1. Loss of a source or breaker status change.
  2. Available capacity below load.
  3. Frequency falling below a threshold.
  4. Battery state of charge low.
  5. High temperature in cooling or electrical room.

Calculation example (illustrative)

Capacity online 1,500 kW (three 500 kW sets). Safe limit 90 percent: 1,350 kW. Load 1,600 kW before an event. After one set trips, capacity 1,000 kW × 0.9 = 900 kW. Shed 700 kW. Tier 4 and 3 loads total 650 kW, so a part of tier 2 is also required.

Do not forget

See load shedding automation and load shedding engineering.

Common mistakes

What to send us

Send the load list, generator data and the events to cover. Send your application details. See also load-shedding planning.

Questions engineers ask

What is the difference between static and dynamic shedding?

Static shedding acts on known capacity and events. Dynamic shedding reacts to measured frequency, catching unforeseen conditions.

How fast must shedding be?

For generator loss it must act before the remaining units stall. That is often within a fraction of a second, so dedicated fast logic is used.

Can shedding be fully automatic?

Usually yes for the first response. Restoration may be automatic or operator-supervised.

How often should the priority list be reviewed?

Whenever loads change, and at least periodically as part of design review.

This guide gives general principles. Settings must be developed and tested for the actual system.