Synchronising and Paralleling Switchgear Guide

How paralleling switchgear lets generators share load: bus design, breakers, sync-check, controllers, load sharing, protection and the points to specify for multi-generator systems.

In short. Paralleling switchgear connects two or more generators to a common bus. It must bring them into synchronism before closing, share load and VAr between them, protect the bus and each generator, and manage start, stop and failure of units.

Main parts

PartFunction
Generator breakersConnect each generator to the bus
BusRated for combined fault level
Synchroniser and sync-checkMatch voltage, frequency, phase before closing
Load-share controllerSplits kW and kVAr between sets. See load sharing
Master controllerStarts and stops units by demand, handles faults
Protection relaysPer generator and bus
Tie / coupler and utility breakersConnect to the rest of the system

Synchronising conditions

Before closing, the incoming generator must match the bus in voltage, frequency and phase angle within narrow limits. Automatic synchronisers adjust speed and voltage; a sync-check relay independently blocks closing if conditions are not met. See synchronisation.

Fault level of the bus

With several generators, the fault level adds up, and the bus and breakers must be rated for the total. The fault current of all sets plus any utility contribution defines the rating. See fault levels.

Specification checklist

Illustrative example

A three-generator plant with 1,000 kVA sets has a 2,000 A bus. The first set to start closes onto the dead bus, the others synchronise and close, and load is shared proportionally. If one set trips, the master controller starts a standby unit and sheds non-essential load if capacity falls short.

The four conditions before closing

Paralleling two AC sources needs matched voltage, frequency, phase angle and phase sequence at the instant of closure. Mismatch creates a surge of current and torque on the machines.

Approximate surge current ≈ ΔV ÷ (Xd” + Xsystem), where ΔV is the vector voltage difference at closing

Typical synchronising windows (illustrative)

ParameterTypical window
Voltage differenceWithin about 5 to 10 percent
Frequency differenceWithin about 0.1 to 0.2 Hz
Phase angleWithin about 10 to 20 degrees at closing

Confirm values from the relay maker and the machine data.

Equipment in a paralleling board

  1. Synchroniser or sync-check relay.
  2. Governor and AVR control interfaces.
  3. Load-sharing controller.
  4. Generator breaker with suitable closing time.
  5. Protection relay package.

Auto vs manual

Automatic synchronisers are standard on modern sets. Manual synchronising with a synchroscope should be backed by a sync-check relay to prevent a bad close.

Dead-bus and live-bus closing

When the bus is dead, the first generator closes onto it. Logic must stop two sets closing onto a dead bus simultaneously.

Related topics

See synchronisation and kW and kVAr load sharing.

Common mistakes

What to send us

Send the generator list, load profile and single-line diagram. Send your application details. See also synchronising switchgear service.

Questions engineers ask

Can different generator sizes run in parallel?

Yes, with proportional load sharing, as long as controls are compatible.

What if sync-check fails?

Closing is blocked. Check speed, voltage and phase sequence.

What is a dead-bus closing?

The first unit closing on an unenergised bus, which needs logic to avoid two closing together.

Is a master controller necessary?

For plants with several units, it manages start, stop, sharing and shedding.

This guide gives general principles. Specification needs project data.