Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

DG Synchronising Panels Guide

What a DG synchronising panel contains and how it works: synchroniser, sync-check, breaker control, metering, load sharing, protection and the commissioning tests that prove a safe paralleling.

In short. A synchronising panel is the control and protection cubicle that brings a generator onto a live bus safely. It matches speed, voltage and phase, closes the breaker only when conditions are safe, and then manages load sharing and protection.

Panel contents

How synchronising works

  1. The controller measures voltage and frequency on both sides of the open breaker.
  2. It adjusts the incoming generator’s speed (and voltage) to match the bus.
  3. When frequency, voltage and phase angle are within the closing window, the controller issues a close signal.
  4. The sync-check relay confirms permissive conditions; otherwise the close is blocked.
  5. After closing, load sharing takes over.

Closing out of phase can cause large currents and torque, damaging the shaft, coupling and windings.

Manual synchronising

Some panels provide manual synchronising with a synchroscope and lamps. It should always be supervised by a sync-check relay, so that an operator error cannot close an out-of-phase breaker.

Commissioning tests

Illustrative example

During commissioning, a technician swaps two phases at a generator terminal. The phase-sequence check shows a mismatch, and the sync-check relay blocks the breaker. After correcting the connection, synchronising proceeds. Without the independent relay, the first closing would have been out of phase.

What a DG synchronising panel contains

SectionFunction
Generator incomer breakerConnects each set to the common bus
Common busDistributes power to load feeders
Synchronising controller per setMatches and closes
Load-sharing and power management controllerShares kW and kVAr, starts and stops sets by demand
Protection relaysPer generator and for the bus
Metering and HMIOperator visibility

Design points

  1. Bus rating must exceed combined fault contribution of all sets plus any utility source.
  2. Breaker closing time and control voltage must suit the synchroniser.
  3. Provide a fallback manual sync mode with sync-check.
  4. Define priority and standby order for sets.

Dead-bus start logic

Define who closes first. A bus-voltage check and an interlock stop two incomers closing onto a dead bus at once.

Control power

Provide reliable DC supply for controllers and breaker coils, with redundancy for critical sites. See DC control power.

Testing and commissioning

See multi-DG load sharing and commissioning.

Common mistakes

What to send us

Send the generator and bus details. Send your application details. See also paralleling switchgear.

Questions engineers ask

What is a synchroscope?

An indicator showing the phase difference and relative speed between two sources.

Why is sync-check separate?

So that a single failure in the synchroniser cannot cause an unsafe close.

Can one panel serve several generators?

Usually each generator has its own panel or section, connected by a bus and communication.

How often should it be tested?

As part of regular testing, and after changes to controls or breakers.

This guide gives general principles. Follow the manufacturer’s commissioning procedures.

CallWhatsAppEnquire
STAGING PREVIEW ยท NOT INDEXED