Utility + ATS/AMF + DG Architecture

The standard backup architecture: utility, automatic transfer switch or AMF panel and diesel generator. Roles, transfer logic, timing, interlocks, neutral switching, testing and failure modes.

In short. Utility, ATS or AMF panel, and a generator form the basic backup chain. The AMF senses mains failure, starts the engine, waits for stable output, transfers the load through an interlocked changeover, and returns when mains is healthy.

Chain

Utility → ATS/changeover ← generator → load. The ATS makes sure the two sources never feed the load together unless designed to.

Sequence

T0 mains fails → T1 delay and start signal → T2 engine cranks and runs → T3 voltage and frequency stable → T4 transfer → T5 retransfer after mains returns with a timer, cool-down and stop.

See ATS and AMF control logic and ATS service.

Design points

ItemWhy it matters
Mechanical and electrical interlockPrevents backfeed and paralleling
Transfer timingSettings avoid nuisance start and unstable transfers
Neutral switchingAffects earth-fault protection. See earthing
Load sheddingIf the generator is smaller than the load. See load shedding
Breaker ratingsFault level and withstand
TestingRegular on-load tests

Open versus closed transition

Open transition has a brief dead time. Closed transition parallels briefly, needing synchronising equipment and utility approval. See synchronisation.

Protection

Coordinate generator, ATS and downstream breakers. See coordination and generator protection.

Illustrative example

A commercial building tests its ATS monthly on load. One test reveals that the ATS retransfer timer is too short and the generator stops before the mains is stable. Adjusting the timers prevents repeated switching during unstable mains.

Timing parameters and what they do

ParameterPurposeRisk if wrong
Mains failure delayIgnore very short dipsToo short: nuisance starts. Too long: longer outage
Engine start and warm-upAllow stable outputShort: transfer onto an unstable set
Generator availability checkVoltage and frequency in rangeMissing check allows poor supply
Transfer timeMechanical switchingLong break for sensitive loads
Mains return delayConfirm stable mainsShort: repeated transfers
Cooling runCool the engine before stopSkipping shortens engine life

See ATS and AMF logic.

Neutral and earthing arrangements

With a three-pole switch, the neutral is common to both sources, and the earth fault protection works the same on both. With a four-pole switch, the generator neutral is separate and bonded at the generator. This affects where earth fault protection is placed and how stray currents flow. The design must be consistent with the earthing system. See earthing.

Testing programme

  1. Monthly: run the generator on load or load bank.
  2. Quarterly: simulated mains failure test on load, where safe.
  3. Annual: full test including protection and alarms.
  4. After any modification: repeat the relevant test.

Common problems found in tests

Records

Log every test, with date, result, defects and fixes. These logs help show diligence and identify trends.

The master engineering question

What does the load see at each moment from T0 to T5, and what could go wrong at each?

What to send us

Send single-line and generator details. Send your application details.

Questions engineers ask

AMF or ATS?

AMF adds start and stop control; ATS is the switching device.

Why does the transfer take time?

Start, warm-up and stabilise delays.

Is neutral switching needed?

Depends on the earthing design.

How often to test?

Regularly, on load.

Values are illustrative. Follow code and maker guidance.