Protection Coordination and Selectivity Guide

How to make the protective device nearest a fault trip first, using time, current and zone methods, with margins, generator considerations and the checks that prove a coordination study.

In short. Coordination, or selectivity, means that when a fault occurs, only the device closest to it trips. It is achieved by grading devices in time, current or zone so that upstream devices wait, while still protecting cables and equipment from damage.

Methods

MethodHow it worksTrade-off
Time gradingUpstream devices have longer delaysFault clearing slower closer to the source
Current gradingDifferent pickup levelsLimited where fault current varies little
Zone selective interlockingDownstream device signals upstream to waitNeeds wiring or communication
Differential or unit protectionTrips only for faults within its zoneHigher cost
Energy-based (cascading) selectivityManufacturer-tested pairs of devicesSpecific products only

Study workflow

  1. Collect device data, settings and cable and transformer ratings.
  2. Calculate maximum and minimum fault levels. See fault levels.
  3. Plot time-current curves from the load back to the source.
  4. Set each device with a grading margin above the one downstream.
  5. Check against damage curves of cables, transformers, motors and the generator.
  6. Repeat for each source mode: utility, generator, and parallel.

Grading margin

The margin allows for the breaking time of the downstream device, relay overshoot and tolerance. The right value depends on the device types. Use manufacturer data rather than a universal figure.

Generator considerations

Illustrative example

A 400 A feeder breaker trips downstream of a 1,600 A incomer. On utility supply, the feeder trips in a few cycles and the incomer waits through its short-time delay. On generator supply, the fault current is lower, and the feeder trips on its short-time region while the incomer still waits. The study shows the two curves separated at both levels, and the settings are recorded for the site.

The principle of time grading

Each protective device nearer the source is set to operate slower than the device downstream, by a margin. When a fault occurs on a feeder, the feeder’s own device trips first; the upstream device sees the fault but does not reach its operating time before the fault is cleared.

Upstream operating time ≥ Downstream clearing time + grading margin

The margin covers breaker opening time, relay overshoot and measurement tolerance. A typical practice uses a margin of a few tenths of a second for relays, with smaller values for modern electronic devices; use the maker’s data.

Methods

MethodUse
Time gradingCommon for overcurrent relays and breakers
Current gradingWhere impedance between devices is large
Zone selective interlockingAllows fast tripping of the nearest device by communication
Energy-based selectivity (current-limiting devices)For MCCB and MCB combinations, per maker tables

Procedure for a coordination study

  1. Draw the single-line diagram with ratings.
  2. Calculate maximum and minimum fault levels.
  3. Plot device curves on a common current axis at one voltage.
  4. Set downstream first, then work upstream.
  5. Check that upstream devices still protect cables and equipment, within their thermal limits.
  6. Document the settings and test them.

Generators and coordination

With a generator source, fault current is lower, so upstream devices may not trip fast enough for a downstream fault. Use settings that work on both sources, or switch setting groups when the generator is supplying. See overcurrent protection.

Typical problems

Illustrative result

After a study, a plant loses a single motor feeder to a fault rather than the whole plant, because upstream breakers now delay long enough for the feeder breaker to clear.

Common mistakes

What to send us

Send relay and breaker data, with the single-line diagram. Send your application details. See also coordination basics and setting philosophy.

Questions engineers ask

What is full selectivity?

Only the device immediately upstream of the fault trips, up to the maximum fault level.

Is full selectivity always possible?

No. Some device combinations give partial selectivity up to a limit, which may be acceptable.

What if there is not enough time margin?

Use zone interlocking, differential protection or different devices.

Why recheck after changes?

New sources, devices or settings alter the curves and the fault levels.

This guide gives general principles. Coordination requires a study with real data.