Generator Plant Master Control Architecture

How a generator plant master controller coordinates sets, breakers, fuel, cooling and auxiliaries, with clear authority, alarms, modes and fall-back when the master or its network fails.

In short. A plant master controller coordinates several generator sets as one power plant. It manages start and stop, sharing, breakers and auxiliaries, but each set keeps its own protection and basic control. The plant should stay safe and share load if the master is lost.

What the master coordinates

Architecture options

OptionDescriptionTrade-off
Central masterOne controller commands all setsSimple, but a single point of failure
Peer-to-peerSet controllers communicate and agreeNo single master; more tuning
HybridPeer sharing with a master for dispatch and reportingCommon in practice

Plant states

Define states such as Stopped, Standby ready, Starting, Synchronising, Running on load, Shedding, Restoring, Fault and Maintenance. Each has entry conditions and permitted actions. See state machines.

Auxiliary readiness

A set that is mechanically ready but has no fuel transfer, no cooling air or a flat starting battery is not available. Include auxiliary status in availability logic. Starting battery state in particular should be monitored, because a failed start system means zero capacity.

Alarms and events

Group alarms into plant-level and set-level. Provide a clear first-out indication so operators see the initial cause. See alarm rationalisation.

Illustrative example

A four-set plant has a master controller. A fuel-transfer pump fault leaves one set’s day tank low. The master marks that set unavailable for the next dispatch, raises a plant alarm with the cause, and dispatches another set instead, so a failed start is avoided.

The plant master as conductor

A generator plant master control coordinates individual set controllers so the plant behaves as one system: it receives a plant-level demand and decides which sets run, at what load.

LevelFunction
Set controllerEngine and alternator protection, governor and AVR interface, synchronising
Plant masterDispatch, sequencing, bus and breaker coordination, load shedding
SupervisoryOperator interface, alarms, history

Core plant master responsibilities

  1. Establish the bus on a mains failure: the first set to reach healthy voltage closes to the dead bus; others synchronise.
  2. Pick the lead and standby sequence, rotating to balance run hours.
  3. Ramp load onto the plant in steps that match engine capability.
  4. Manage the tie to the utility.

Failure handling

If the plant master fails, each set controller must hold its last state or fall back to droop sharing. The plant should not black out because a supervisory device failed.

Parameters to document

ParameterExample
Start-up delay per setSeconds from start to breaker closure
Step sizePercent of rating per load step
Minimum run timeMinutes before auto-stop
Fail-to-start timeoutSeconds before the next set is called

See multi-DG sequencing and PMS architecture.

The master engineering question

Does the master know which sets can truly carry load right now, including their auxiliaries, and what does each set do on its own if the master stops?

What to send us

Send the plant layout, set data and auxiliary list. Send your application details.

Questions engineers ask

Do identical sets simplify control?

Yes. Mixed sets are possible but need more careful sharing and dispatch rules.

Should the master also control fuel?

It should at least monitor fuel and auxiliary availability.

What about remote operation?

Allow with authority rules. See control philosophy.

Can the master be replaced later?

If interfaces are standard, yes.

This guide gives general principles. Confirm with a project design.