Multi-DG Automatic Sequencing and Dispatch Control

How multiple generators start, stop and load automatically: load-dependent thresholds, priority rotation, reserve rules, failure replacement and the timing that keeps the bus stable.

In short. Automatic dispatch runs only as many sets as the load needs, while keeping enough reserve to survive the largest credible event. Thresholds, delays, priority rotation and failure replacement must be tuned together, or the plant will either hunt on and off or run short of margin.

Dispatch rules

RulePurpose
Start thresholdStart another set when load exceeds a percentage of running capacity for a set time
Stop thresholdStop a set when remaining sets can carry load with margin for a set time
HysteresisGap between start and stop thresholds to avoid cycling
Priority and rotationBalance run hours and keep the best sets ready
Reserve ruleMaintain capacity to lose the largest running set
Failure replacementStart the next available set if one trips

Sequence of a start

Demand detected → start command → crank → run → voltage and frequency acceptable → sync check → breaker close → load ramp → sharing active. Each step has a timeout. If a set fails to start, the next set is called.

Sequence of a stop

Stop condition → unload ramp → breaker open → cool-down → stop → return to standby. Do not stop sets in a way that leaves the plant below reserve.

Timing issues

Engine considerations

Running engines at very low load for long periods causes wet stacking and fouling. Dispatch should avoid prolonged light loading, and plan periodic higher-load running. See load-bank testing.

Illustrative example

A plant with three 1,000 kVA sets runs one set to 80 percent load, then starts a second after a 10 second delay. When load falls below 40 percent of two-set capacity for 5 minutes, the second set unloads and stops. If the running set trips, the next set starts, and the PMS sheds low-priority loads until it takes over. See PMS architecture.

The sequence on a mains failure (illustrative timings)

StepEventTypical time
1Mains failure detected and confirmed1 to 3 s
2All standby sets receive start commandImmediate
3First set at rated voltage and frequency closes to dead bus8 to 15 s
4Other sets synchronise and close5 to 10 s each
5Load added in priority stepsSeconds between steps
6Surplus sets stop if demand is lowAfter minimum run time

Dispatch rules

  1. Order of start by priority and run hours.
  2. Start a further set when loading passes the upper threshold for a delay time.
  3. Stop a set only if the others can carry the load with margin.
  4. Keep the N+1 standby available.

Fail-to-start handling

If a set fails to start in the allowed time, the next set is called without waiting for operator action, and an alarm records the fault. If capacity is insufficient, automatic load shedding limits the load to what is available.

Dead-bus closing safety

Only one breaker may close to a dead bus. Hardware interlock plus logic ensures this. See dead-bus and live-bus logic.

See N+1 design.

The master engineering question

At each load level, how much margin does the running fleet have against the worst credible event, and how long does the next set need to arrive?

What to send us

Send load profile and set data. Send your application details.

Questions engineers ask

Why do sets keep starting and stopping?

Thresholds or delays are too close. Increase hysteresis and delay.

Should I rotate priority?

Yes, usually, to balance wear. Keep sets in good health ready.

How much reserve?

Defined by the redundancy level and worst credible event.

Can dispatch use load forecasts?

Yes, via an EMS, within PMS safety limits.

Values are illustrative. Tune on site.