ATS, STS and UPS Architecture Selection Guide

How to choose between ATS, STS, UPS and combinations for a load: transfer time needs, source types, load sensitivity, cost and maintenance, with a selection table and examples.

In short. Choose by the interruption the load can tolerate. If seconds are acceptable, an ATS with a generator is enough. If milliseconds matter between two clean sources, use an STS. If no break is acceptable, use a UPS, often with an STS and a generator behind it.

The decision table

Load toleranceSources availableSuggested architecture
Seconds to minutesUtility and generatorATS
Fraction of a second, single-cordedTwo clean feedsSTS
None, with generator backupUtility, generatorOnline UPS plus ATS and generator
None, highest availabilityTwo independent systemsDual UPS with dual-cord loads, or UPS with STS
Poor-quality supply, brief outages acceptedUtility onlyStabiliser, or line-interactive UPS
Both quality and continuityUtility and generatorOnline UPS plus ATS

Role of each device

Typical combined arrangement

Utility and generator feed an ATS. The ATS feeds the UPS input and non-UPS essential loads. The UPS feeds critical loads. If a second UPS or path exists, an STS or dual-cord arrangement joins them. Coordination of timing and settings matters. See ATS, STS and UPS coordination.

Questions to ask

  1. What is the load’s ride-through time?
  2. Is the load dual-corded or single-corded?
  3. What are the sources, and are they synchronised?
  4. What fault levels and protection exist?
  5. How will the system be maintained while live?

Other selection points

Worked illustration

A manufacturing plant has process loads that ride through two seconds, and a 40 kW control and IT room that cannot. The design: one ATS for the plant between utility and generator, and a 40 kW online UPS behind the ATS for the control room. No STS is needed because the loads are not single-corded across two sources. Adding STS or dual UPS would raise cost without benefit.

Which switch for which job

NeedDevice
Move a board between utility and generatorATS
Switch a load between two clean synchronised sources in millisecondsSTS
Hold the load with no break through an outageUPS
Allow service of a UPS without dropping loadMaintenance bypass
Give single-cord equipment two feedsRack STS

Typical arrangements

  1. ATS upstream, UPS downstream: common and simple; the UPS rides through the ATS transfer.
  2. Two UPS systems, STS at the load: removes UPS as a single point of failure for single-cord loads.
  3. Dual-bus with dual-cord loads: no STS needed for those loads.

Selection checks

Example (illustrative)

A data room with dual-cord servers and some single-cord network devices: two UPS systems on A and B buses fed from separate ATS-backed generator sections; rack STS for the single-cord devices.

See transfer coordination and static transfer switch systems.

Common mistakes

What to send us

Send load ride-through data and supply details. Send your application details.

Questions engineers ask

Do I need both ATS and STS?

Not always. ATS serves the utility to generator change; STS serves two clean sources for single-corded loads.

Can a UPS replace an ATS?

No. It bridges short gaps; the ATS connects the generator for longer outages.

When is a four-pole ATS needed?

When the neutral must be switched to keep source earthing separate.

What transfer time can an ATS achieve?

Open transition is typically tens to hundreds of milliseconds, plus the generator start time before it.

This guide gives general principles. Selection needs a design review.