ATS / AMF Control Logic Engineering

How ATS and AMF controller logic is built: inputs, source qualification, start and transfer states, test modes, alarms, fail-safe behaviour and checks that prove standby readiness.

In short. AMF and ATS logic turns source measurements and breaker states into start and transfer decisions. Good logic is a clear state machine with qualified inputs, timeouts, interlocks and alarms. The most common real failure is not the logic but the system left in the wrong mode.

Inputs

States

StateEntryExit
Normal on utilityUtility OKUtility fails for set time
StartingStart commandGenerator running or fault
Warm-up and stabiliseRunningSource acceptable
On generatorTransfer completeUtility returns for set time
RetransferReturn confirmedTransfer complete
Cool-downOff loadTimer ends
Fault or lockoutProtection or failed sequenceManual reset

Interlocks

The two source breakers must be mechanically or electrically interlocked so both cannot close together. Use feedback from auxiliary contacts to confirm positions, not only command outputs. See interlocking.

Test modes

Define who may run each test and ensure the system returns to AUTO afterwards.

Alarms for readiness

  1. Not in AUTO.
  2. Low fuel, low coolant, low battery voltage, charger fault.
  3. Breaker not in service position.
  4. Failure to start or transfer.
  5. Controller fault or communication loss.

Neutral and earthing

Where the generator neutral is earthed, switch the neutral during transfer. See earthing architecture and ATS service.

Illustrative example

After a service visit, a generator is left in MANUAL. On the next outage, nothing starts. The fix is not only better training but also an alarm and a remote indication that shows “Standby not ready” whenever the selector is not in AUTO, plus a post-service checklist step.

A state machine for AMF

StateEntry conditionExit
Mains healthyVoltage and frequency within windowMains out of window for failure delay
Start sequenceFailure confirmedEngine running or failure to start
Warm-upEngine runningVoltage and frequency stable for set time
On generatorTransfer completedMains healthy for return delay
RetransferMains stableLoad back on mains
Cool-downGenerator off loadTimer complete, engine stops
Fail-to-startCrank attempts exhaustedAlarm, lockout, reset

Start attempts

Typical cranking: three attempts of 5 to 10 seconds with 5 to 10 second rests, with the starter protected against overheating. After the last failure, alarm and lock out.

Permissives for transfer

  1. Generator voltage and frequency inside the window.
  2. Mains breaker confirmed open (or interlock released).
  3. No generator protection trip active.
  4. Mode in automatic.

Abnormal sequences to design for

See interlocking and state machine engineering.

The master engineering question

At this moment, if the utility failed, would everything in the chain be ready, and how would anyone know without a test?

What to send us

Send controller model and the single-line diagram. Send your application details.

Questions engineers ask

What is the difference between AMF and ATS?

AMF starts the generator; ATS switches the load. Many panels combine both.

Why feedback from the breaker?

A command does not prove the breaker moved.

How often to test?

Regularly, including on-load tests, per site policy.

Can logic be customised?

Yes, within the controller’s limits and with documented testing.

This guide gives general principles. Follow the manufacturer’s instructions.