Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Critical-Load Restoration and Restart Sequencing

How to restart loads after an outage in stages that the generator can handle: sequencing, delays, motor and inrush effects, UPS recharge and the settings that prevent a second trip.

In short. After an outage or a transfer, switching every load back at once can overload the generator and cause a second blackout. Restoration should bring loads on in stages, largest or most critical first where appropriate, with delays so voltage and frequency settle between steps.

Why restart needs design

Loads draw more at start than in running: motors may pull five to seven times full-load current, transformers draw inrush, UPS rectifiers and chargers draw recharge current, and refrigeration and cooling loads restart together. The sum can far exceed the generator’s step capacity.

What sets the stage size

ConstraintMeaning
Generator step capabilityMaximum block load that keeps voltage and frequency within limits
Voltage dip limitContactors and sensitive loads must not drop out
Frequency recoveryEngine speed and governor recovery time
Transformer inrushSeveral times rated current for a few cycles
Process dependenciesSome loads must start before others

See load-step screening and motor-starting capacity.

Building the sequence

  1. Group loads into steps no larger than the generator can accept.
  2. Order steps by priority and dependency: controls and cooling before process loads, for example.
  3. Insert delays that let voltage and frequency recover, typically several seconds per step, to be confirmed on site.
  4. Use permissive signals where possible: the next step starts when the generator reports stable output.
  5. Limit the largest motor starts using soft starters or drives.

Special cases

Automatic versus manual

Automatic sequencing is faster and repeatable, and suits unattended sites. Manual restoration lets operators judge conditions but depends on staffing and training. Some sites automate the first tiers and leave the rest to operators. See automatic restoration control.

Worked illustration

A generator of 800 kVA must restore 600 kW of load including a 150 kW pump with direct-on-line starting. If all loads return together, the pump’s starting current of about six times its full-load current coincides with transformer inrush and UPS recharge, and the generator voltage collapses. A sequence is created: step 1, control and lighting at 0 s; step 2, cooling fans at 10 s; step 3, the 150 kW pump on a soft starter at 20 s; step 4, UPS rectifier with a 30-second walk-in at 30 s; step 5, deferrable loads at 60 s. Each step is within the generator’s capability.

Verification

Restart is a design problem

When power returns, chillers, compressors, pumps and UPS rectifiers all want to start at once. Their combined inrush can exceed the source and cause another outage. Sequencing spreads the demand.

StepLoad groupTypical delay
1Controls, lighting, IT, monitoringImmediate
2UPS input (with walk-in)5 to 15 s
3Cooling circulation pumps and fans10 to 30 s
4Chillers one by one30 to 60 s each
5Non-critical loadsLast, when source loading is stable

Constraints on restart

Check each step

  1. Is the voltage and frequency within limits before the next step?
  2. Is generator loading below the allowed block?
  3. Has the previous load reached steady state?

When mains returns

After transfer back, the load transient repeats. Re-sequence rather than closing all loads at once.

See automatic restoration and motor starting.

Common mistakes

What to send us

Send the load list, motor sizes and start methods. Send your application details. See also load shedding.

Questions engineers ask

Why did the generator trip after power came back?

The combined restart load of motors, transformers and chargers likely exceeded its step capability. Sequencing fixes this.

How long should delays between steps be?

Long enough for voltage and frequency to recover. Determine this by testing, not by a fixed rule.

Does a soft starter help?

Yes. It reduces starting current and the voltage dip, so larger motors can be added in fewer steps.

Should restoration be automatic?

For unattended and critical sites, usually yes, with an operator override.

This guide gives general principles. Sequences must be tested on the real system.