Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

UPS Battery Autonomy and Runtime Engineering

How to choose UPS battery autonomy from generator start time and shutdown needs, the factors that reduce real runtime, and how to verify and maintain it over the battery's life.

In short. Battery autonomy is the time a UPS can carry its load after the supply fails. Choose it from what the battery must bridge: generator start and transfer, a failed first start, and, where needed, an orderly shutdown. Quoted runtime is a new-battery figure at specific conditions, so apply allowances for age, temperature, discharge rate and end voltage.

What autonomy must cover

  1. Time for the generator to start, reach rated voltage and frequency, and transfer.
  2. Time for a second start attempt if the first fails.
  3. Time for operators to respond to alarms.
  4. Time for an orderly shutdown of IT or process equipment if no source returns.

Where a generator is present, minutes are usually enough. Where there is none, autonomy must cover the entire outage or a shutdown.

Basic energy estimate

Battery energy required (kWh) ≈ Load (kW) × Autonomy (h) ÷ (Inverter efficiency × Usable depth of discharge × Ageing factor)

Example, illustrative only: a 100 kW load, 10 minutes autonomy, inverter efficiency 0.95, usable depth of discharge 0.8 and an ageing and temperature factor of 0.8.

Energy = 100 × (10 ÷ 60) ÷ (0.95 × 0.8 × 0.8) = 16.7 ÷ 0.608 ≈ 27 kWh. Manufacturers size by discharge tables at a constant power rate to an end voltage, which is more accurate than this estimate, so use their data for the final selection.

Why real runtime is shorter than catalogue runtime

FactorEffect
Battery ageCapacity falls over life; a common end-of-life point is about 80 per cent of rated
TemperatureCold reduces available capacity; hot shortens life
High discharge rateShort autonomy at high power gives less usable energy per kWh
End-of-discharge voltageA higher cutoff cuts the usable energy
Load growthMore load, less time
Weak cellsOne bad cell can reduce a string’s performance

Battery technology considerations

Select by life-cycle cost, space, temperature and the site’s safety rules.

String arrangement

Use more than one string in parallel where the design allows, so a single string fault does not remove all autonomy. Provide isolation so one string can be maintained while others remain online. See battery monitoring.

Verification

Runtime is not nameplate times load

Battery capacity in Ah at a 10 hour rate is not available at a 10 minute discharge. High discharge rates reduce usable capacity. Battery voltage is not capacity: a bank can sit at correct float voltage and still fail on load.

Required battery power per cell = (load kW ÷ inverter efficiency) ÷ number of cells, for the specified time to end-voltage

Sizing steps (illustrative)

  1. Load: 200 kW, inverter efficiency 95 percent: DC power 210.5 kW.
  2. Autonomy target: 10 minutes.
  3. Choose battery from the maker’s discharge table (watts per cell at 10 minutes to end voltage).
  4. Apply ageing factor 1.25 and temperature correction.
  5. Check recharge time and charger rating.

Factors that shrink runtime

FactorEffect
Age (end of life at 80 percent capacity)Reduces runtime by about 20 percent
Low temperatureReduces capacity
High temperatureShortens life, roughly halving life for every 8 to 10 degrees above 25 °C
Weak cells in stringOne weak cell limits string

Testing and monitoring

Hyderabad’s summer heat shortens battery life if the battery room is not cooled. Follow the manufacturer’s guidance and applicable standards. See battery systems.

Common mistakes

What to send us

Send your load, the generator start time, the temperature range and the autonomy you require. Send your application details. See also UPS autonomy guide.

Questions engineers ask

How many minutes of UPS autonomy do I need?

Enough to cover generator start, transfer and a failed first attempt, plus margin. Where no generator exists, enough to ride through or shut down in order.

Why does my UPS give less time than the catalogue says?

Catalogue times are for new batteries at set conditions. Ageing, temperature, load and cutoff voltage all reduce the real figure.

How often should batteries be replaced?

By measured health and manufacturer guidance. Many VRLA installations replace in a window of several years, depending on temperature and use.

Is lithium-ion better than lead-acid for UPS?

It can offer longer life and smaller size, but cost and safety design differ. Compare life-cycle cost for your site.

Does adding load affect autonomy?

Yes. Autonomy falls faster than linearly at higher discharge rates, so recheck after load changes.

Figures here are illustrative. Use manufacturer discharge data for final sizing.

CallWhatsAppEnquire
STAGING PREVIEW · NOT INDEXED