Generator Capacity Requirement: From Load to Preliminary Size

A step-by-step method for estimating the generator capacity a site needs: running load, power factor, starting, derating, redundancy and growth, with a worked example and limits of the estimate.

In short. Generator capacity is the largest of three checks: the running load with margin, the load after the biggest start or step, and the load with one unit out of service where redundancy is required. This guide walks through each check and shows why one calculation is never enough.

Three capacity checks

CheckQuestion
Running capacityCan the generator carry the steady load with margin?
Transient capacityCan it start the largest motor or take the biggest step within voltage and frequency limits?
Redundancy capacityWith one unit down, can the rest carry the critical load?

Running capacity

Required kVA = (Maximum demand kW ÷ power factor) × (1 + growth) ÷ (derating factor × target loading)

Example (illustrative): demand 420 kW, power factor 0.85, growth 15 per cent, derating factor 0.95 for a hot site, target loading 0.8.

Required kVA = (420 ÷ 0.85) × 1.15 ÷ (0.95 × 0.8) = 494 × 1.15 ÷ 0.76 ≈ 747 kVA. A 750 kVA unit is the nearest, but is at its limit, so 800 kVA or a different arrangement might be considered. Check the actual derating from the manufacturer’s data. See derating.

Transient capacity

Check the largest motor start with other loads running, and the largest step. Voltage dip and frequency dip must stay within the limits that the loads and controls can tolerate. See motor-starting capacity and load-step screening.

Redundancy capacity

For N+1 designs, divide the critical load across units so that the remaining units carry it. For example, a 1,500 kVA critical load with N+1 using units of 750 kVA needs three units: two carry 1,500 kVA, one spare. See number of generators.

Choosing one large or several small units

Things that change the answer

Limits of a preliminary estimate

This is a screening method. Final capacity needs verified loads, the manufacturer’s performance data and often a transient study. It is better to find that an apparently adequate generator has a problem at the screening stage than at commissioning.

A capacity requirement in five numbers

NumberMeaning
A. Running demand (kW)Load to be carried continuously
B. Power factorConverts to kVA
C. Largest motor start (kVA)Peak step to survive
D. Derating (percent)Site temperature and altitude loss
E. Growth margin (percent)Planned expansion

Worked example (illustrative)

A = 450 kW, B = 0.85, so 529 kVA running. D: 8 percent loss in summer heat, so required nameplate = 529 ÷ 0.92 = 575 kVA. E: 15 percent growth, 575 × 1.15 = 661 kVA. Choose a 750 kVA class unit if standard ratings are 625 and 750. Then verify the largest motor start and transient limits. If those fail, the answer changes: the starting check often forces a larger alternator.

Duty class

Select the rating class with the maker’s definition. See standby power and prime power.

Next steps

Confirm with motor-starting guide and derating guide.

Common mistakes

What to send us

Send your demand data, motor list, site conditions and redundancy target. Send your application details. See also kVA and kW sizing.

Questions engineers ask

What target loading should I use?

Many designs aim for about 70 to 80 per cent of rating at the design load, but the right figure depends on duty and the manufacturer’s guidance.

Do I size for the largest motor start?

You must check it. The size that handles the running load may fail at the biggest start.

How does redundancy change the size?

It adds units so that the critical load is carried with one unit out.

Is one big generator or several better?

It depends on redundancy needs, load profile and space. Several units add resilience and flexibility.

Figures are illustrative. This is a screening method, not a final design.