Reddy GeneratorsREDDY GENERATORSThe dependable power professionals

Critical-Power Monitoring, SCADA and Power Analytics

What to monitor in a critical-power system, how SCADA and analytics turn data into early warning, and how to design alarms, history and remote access without adding new failure points.

In short. Monitoring shows whether the system is ready before it is needed. A good design measures the right points, reports to a supervisory system, keeps history for diagnosis, and raises alarms that people can act on. The monitoring itself must not become a single point of failure or a security risk.

What to monitor

AreaExamples
SourcesUtility voltage and frequency, generator status, fuel level, battery voltage
TransferATS position, STS state, source availability, transfer counts
UPS and BESSLoad, battery health, state of charge, bypass status, alarms
DistributionBreaker status, currents, voltages, power factor, harmonics
ProtectionRelay health, trips, settings group
SupportCooling, ventilation, room temperature, leak detection

Readiness indicators

Specific signals indicate whether the system can respond: generator in auto, no latched alarms, start battery voltage OK, fuel above minimum, transfer switch healthy, UPS on line with battery charged. Present them on one readiness screen so the state is obvious.

SCADA architecture

Analytics that help

Design principles

  1. Control must not depend on SCADA. Equipment keeps working if the supervisory system is down.
  2. Alarms must be prioritised and actionable. See alarm and event management.
  3. Remote access must be secured. See OT network architecture.
  4. Monitoring power must come from a protected supply.

Worked illustration

A site’s dual path loads are each about 45 per cent of rating, tracked on a dashboard. Over a year the sum creeps to 58 per cent on one path. A threshold alarm at 50 per cent warns before the redundancy margin is gone, and the team balances load. Without the trend, a failover would have overloaded the surviving path. The analytics value was in watching the margin, not the failure.

What to watch, and why

SignalEarly warning of
UPS battery voltage, temperature, internal resistance trendWeak cells, ageing
Generator starting battery voltage and charger statusStart failure
Fuel level and quality indicatorsAutonomy and fuel degradation
Path A and path B loadingLoss of redundancy by creep above 50 percent
Breaker temperatures and thermographyLoose connections
Power quality: THD, unbalance, voltage sagsStress on equipment
Room temperatureCooling issues

Analytics that pay back

  1. Capacity headroom per path, per source.
  2. Trending of battery and generator readiness.
  3. Alarm statistics showing repeat events.
  4. Run-hour and fuel consumption tracking.
  5. Event reconstruction after any disturbance.

Architecture

Meters and relays feed a gateway to the SCADA or monitoring platform, with a local view that works if the central link fails. Time-sync the devices so events line up.

Operating practice

Define who watches the data, who is called on an alarm and what each alarm requires. Monitoring without response is decoration.

See SCADA architecture and alarm and event management.

Common mistakes

What to send us

Send equipment lists and any existing monitoring. Send your application details. See also SCADA and BMS monitoring.

Questions engineers ask

What should I monitor first?

Readiness of sources and transfer equipment, battery health and per-path loading.

Can SCADA control the system?

It can supervise and command, but critical control should be local so it survives SCADA failure.

How long should data be kept?

Long enough to diagnose events and trends; follow your records policy.

Is remote monitoring safe?

With proper network design, authentication and segmentation, yes. Treat it as a security design task.

This guide gives general principles. Cybersecurity and network design require specialist input.